Project A has an IRR of 13% and an NPV of $32,011. Project B has an IRR of 11% and an NPV of $265,012. Between
Project A has an IRR of 13% and an NPV of $32,011.
Project B has an IRR of 11% and an NPV of $265,012. Between A and B, a company with a hurdle rate of 7% would prefer to choose ______