Project A Project B Project C Project D Project E Time 0 10,000 10,000 10,000 10,000 10,000 Time 1 5000 4000 3000 4000 2000 Time
Project A | Project B | Project C | Project D | Project E | |
---|---|---|---|---|---|
Time 0 | 10,000 | 10,000 | 10,000 | 10,000 | 10,000 |
Time 1 | 5000 | 4000 | 3000 | 4000 | 2000 |
Time 2 | 4000 | 3000 | 4000 | 4000 | 6000 |
Time 3 | 3000 | 10,000 | 5000 | 4000 | 10,000 |
If WiseGuy Inc is choosing one of the above mutually exclusive projects (Project A or Project B), given a discount rate of 8%, which should the company choose?