Project A: What is the critical path(s) for this project? (hint: do both short cut method and ES-EF method) Activity Immediate Predecessor Activity Duration (days)
Project A: What is the critical path(s) for this project? (hint: do both short cut method and ES-EF method) Activity Immediate Predecessor Activity Duration (days) A B A 5 B A D 12 CE 7 G E,F 9 O ABCFG and ADEG O ADEFG and ADEG O ADEFG O ABCFG