Project B cost $4,900 and will generate after-tax net cash inflows of $500 in year one, $1,300 in year two, $2,100 in year three,
Project B cost $4,900 and will generate after-tax net cash inflows of $500 in year one, $1,300 in year two, $2,100 in year three, $2,500 in year four, and $2,100 in year five. What is the NPV using 10% as the discount rate? Round your present value factor to three decimal places and the rest to nearest dollar. (Click here to see present value and future value tables)