Question

1 Approved Answer

PROJECT B Project B costs is RM 1 . 3 million excluding the purchase of fixed asset of RM 2 5 0 , 0 0

PROJECT B
Project B costs is RM1.3 million excluding the purchase of fixed asset of RM250,000. The cash flows are RM540,000 in year one, RM500,000 in year two, RM560,000 in year three, RM450,000 in year four and the final year is RM200,000. At the termination of the project, 50% of the fixed asset value can be recovered. Assume cost of project of 8.13%.
QUESTION:
1. Initial Outlay is RM_____________.
2. Terminal value is RM_______________.
3. Total PV is RM_________________.
4. Total FV is RM____________.
5. PP is __________.
6. DPP is __________.
7. NPV is RM____________.
8. PI is __________.
9. IRR is _________%.
10. MIRR is _________%.
11. EAA is RM____________.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial management theory and practice

Authors: Eugene F. Brigham and Michael C. Ehrhardt

12th Edition

978-0030243998, 30243998, 324422695, 978-0324422696

More Books

Students also viewed these Finance questions