.) Project BUILD is under review by Mayor Lewis just 3 months after launch as there has been entire presentations at question time in City

.) Project BUILD is under review by Mayor Lewis just 3 months after launch as there has been entire presentations at question time in City Council about over-budgeting in the Roads & Highways Department. Some councilors who previously supported this project are now joining the ranks of those opposing the continuation of the project.

BUILD was planned to be completed in 12 months. The project scope was the asphalt paving of 40 km of Roadway across difficult mountainous terrain. So far, the finance department has reported that $750,000 has been sunk into the project already and the project engineers report that 15 kms of highway has been completed.

The project plan details 5 main work package and 3 control accounts.

Mayor Lewis, with elections in 3 months, is facing enormous pressure to shut the project down or to revise the budget allocations for BUILD. Can your team advise him? Select a project manager, and provide a final report and presentation that includes answers to the questions below.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions