Project Charter GREEN HAVEN RESIDENCE Scope Overview:This project's scope is to design and construct a new modern eco-friendly residence. The project will include the following
Project Charter
GREEN HAVEN RESIDENCE
Scope Overview:This project's scope is to design and construct a new modern eco-friendly residence. The project will include the following major deliverables:
- Architectural design of the eco-friendly residence.
- Construction of an eco-friendly residence with sustainable materials and energy-efficient features.
- Installation of renewable energy systems such as solar panels. Landscaping with native plants and sustainable irrigation systems.
- Implementation of smart home technology for energy management and security.
This project does not include ongoing maintenance and management of the residence after construction.
Business Case - Objective: The objective of this project is to make a modern eco-friendly residence that aligns with sustainable living principles and serves as a model for environmentally conscious construction. By undertaking this project, we aim to:
- Demonstrate our commitment to sustainability and environmental responsibility.
- Showcase the latest eco-friendly technologies and building practices.
- Provide a comfortable and energy-efficient living space for the homeowner.
- Potentially serve as a showcase property for future eco-friendly projects.
This project aligns with our organization's mission to promote sustainable living and environmentally responsible construction practices.
Milestone Schedule
Milestone | Completion Date | Stakeholder Judge |
Architectural design approval | 10/1/2023 | Project Manager, Architect |
Commencement of construction | 12/05/2023 | Project Manager, Construction Team |
Completion of construction | 03/30/2024 | Project Manager, Construction Team |
Installation of renewable energy systems | 06/15/2024 | Project Manager, Energy Experts |
Landscaping and garden completion | 08/30/2024 | Project Manager, Landscaping Team |
Smart home technology integration | 10/25/2024 | Project Manager, Technology Experts |
Final inspection and homeowner handover | 11/10/2024 | Project Manager, Homeowner |
Major Risks
Project Risks | Risk Owner | Response Plans |
Regulatory approvals and permit delays | Expedite permit applications and engage with regulatory authorities proactively. | |
Weather-related construction disruptions Construction Team Monitor weather forecasts and plan construction schedule accordingly. | ||
Availability of sustainable materials and technologies | Identify alternative suppliers and materials in case of shortages. | |
Resources Needed
Funding: $1000,000 Time: 100% of time for 13 months Personnel: Project manager, architects, construction team, energy experts, landscaping team, technology experts, regulatory experts, and support staff. Equipment: Construction equipment, tools, renewable energy system components. Materials: Sustainable construction materials, energy-efficient appliances, smart home technology.
Stakeholder List
Stakeholders | Interest in Project |
Homeowner | Eco-friendly residence, project success |
Project Team | Successful project planning and execution |
Architects | Design and aesthetics |
Construction Team | Timely and quality construction |
Energy Experts | Installation of renewable energy |
Landscaping Team | Eco-friendly landscaping |
Technology Experts | Smart home technology implementation |
Regulatory Authorities | Permit approvals and compliance |
Team Operating Principles
- Commitment to sustainability: All team members are committed to following eco-friendly and sustainable construction practices throughout the project.
- Regular progress meetings: Weekly meetings to review project progress, address issues, and ensure alignment with project goals.
- Transparent communication: Open and honest communication among team members to resolve any challenges promptly.
- Adherence to regulations: Strict adherence to environmental regulations and building codes.
- Lessons Learned
Clear communication with regulatory authorities is crucial to avoid delays.
- Sustainable material sourcing requires early planning.
- Regular team meetings enhance collaboration and problem-solving.
- Incorporating energy-efficient features from the project's outset is cost-effective.
- Signatures and Commitment
Sponsor | Signature |
Core Team Members | Signature |
Neha Sharma | Neha Sharma |
Lexi Johnson | Lexi Johnson |
Sharon Martzell | Sharan Martzell |
HERE IS THE QUESTION'S OF PART 1, 2 AND 3, ANSWER ALL THE QUESTION ON THE BASE OF MY PROJECT CHARTER WHICE I ADDED ABOVE (Part 1- 50 points), (Part 2 and 3 - 100 points)
PART 1 - due date on course calendar on last page of syllabus
Introduction
The Introduction provides a high-level overview of the project and what is included in this Project Management Plan. This should include a high-level description of the project and describe the project deliverables and benefits. This section should provide a summarized framework of the project and its purpose. Look back at the Project Charter for information to include in this section.
Project Scope
State the scope of the project in this section. The scope statement from the project charter should be used as a starting point; however, the project plan may include a more detailed scope than the charter. This detail should include what the project does and does not include. This will help to clarify what is included in the project and help to avoid any confusion from project team members and stakeholders.
Milestone List
Provide a summary list of milestones including dates for each milestone. Include an introductory paragraph in this section which provides some insight to the major milestones. This section should also mention or discuss actions taken if any changes to the milestones or delivery dates are required. To add more rows to the chart below or to delete, right click and select "insert - rows below" or "delete cells."
Milestone | Description | Completion Date | Stakeholder Judge |
Work Breakdown Structure
The WBS provides the work packages to be performed for the completion of the project.
Work Breakdown Structure |
|
PART 2 - due date on course calendar on last page of syllabus
Communications Management Plan
The purpose of the Communications Management Plan is to define the communication requirements for the project and how information will be distributed to ensure project success. You should give considerable thought to how you want to manage communications on every project. By having a solid communications management approach you'll find that many project management problems can be avoided. In this section you should provide an overview of your communications management approach. Generally, the Communications Management Plan defines the following:
Communication requirements based on roles
What information will be communicated
How the information will be communicated
When will information be distributed
Who does the communication
Who receives the communication
To add more rows to the chart below or to delete, right click and select "insert - rows below" or "delete cells."
Communication Type | Description | Frequency | Format | Participants/ Distribution | Deliverable | Owner |
Project team directory for all communications is:
Name | Title | E mail | Office Phone | Cell Phone |
Communications Conduct:
Meetings:
Email:
Informal Communications:
Cost Baseline
This section contains the cost baseline for the project upon which cost management will be based. To add more rows to the chart below or to delete, right click and select "insert - rows below" or "delete cells."
Project Phase | Budgeted Total | Comments |
Procurement Management Plan
The Procurement Management Plan should be defined enough to clearly identify the necessary steps and responsibilities for procurement from the beginning to the end of a project. The project manager must ensure that the plan facilitates the successful completion of the project and does not become an overwhelming task in itself to manage. The project manager will work with the project team, contracts/purchasing department, and other key players to manage the procurement activities.
PART 3 - due date on course calendar on last page of syllabusSchedule Management Plan
This section provides a general framework for the approach which will be taken to create the project schedule. Effective schedule management is necessary for ensuring tasks are completed on time, resources are allocated appropriately, and to help measure project performance. This section should include discussion of the scheduling tool/format and schedule development roles and responsibilities.
Quality Management Plan
This section discusses how quality management will be used to ensure that the deliverables for the project meet a formally established standard of acceptance. All project deliverables should be defined in order to provide a foundation and understanding of the tasks at hand and what work must be planned. Quality management is the process by which the organization not only completes the work, but completes the work to an acceptable standard. Without a thorough Quality Management Plan, work may be completed in a substandard or unacceptable manner. This section should include quality roles and responsibilities, quality control, quality assurance, and quality monitoring.
Risk Management Plan
This section provides a general description for the approach taken to identify and manage the risks associated with the project. It should be a short paragraph or two summarizing the approach to risk management on this project. It should also include the major risks that you identified on the Project Charter document.
Staffing Management Plan
Discuss how you plan to staff the project. This section should include discussion on matrixed or projectized organizational structure depending on which is being used for this project. This section should also include how resources will be procured and managed as well as the key resources needed for the project.
Quality Baseline
This section should include the quality baseline for the project. The purpose of this baseline is to provide a basis for ensuring that quality can be measured to determine if acceptable quality levels have been achieved. It is important for all projects to clearly define and communicate quality standards and the quality baseline serves this purpose. To add more rows to the chart below or to delete, right click and select "insert - rows below" or "delete cells."
Item | Acceptable Level | Comments |
Sponsor Acceptance
Approved by the Project Sponsor:
Date:
Approved by the Project Manager:
Date:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started