Question

1 Approved Answer

Project Management 1. The following activities are part of a project to be scheduled using CPM. Activity Immediate Predecessor Time/Duration (Weeks) A --- 6 B

Project Management

1. The following activities are part of a project to be scheduled using CPM.

Activity Immediate Predecessor Time/Duration (Weeks)

A --- 6

B A 3

C A 7

D C 2

E B, D 4

F D 3

G E, F 7

a. Draw the network.

b. What is the critical path?

c. How many weeks will it take to complete the project?

d. How much slack time does activity B have?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management A Practical Introduction

Authors: Angelo Kinicki, Brian Williams

1st Edition

0078094054, 978-0078094057

More Books

Students also viewed these General Management questions

Question

33. How does DES differ from 3DES? From RC4? From AES?

Answered: 1 week ago