Question
Project Management (35 Points) For a particular project, activities required to complete the project, the precedence relationships for the activities, and activity time estimates, as
Project Management (35 Points) For a particular project, activities required to complete the project, the precedence relationships for the activities, and activity time estimates, as shown in the following table: Activity Activity Predecessor Time Estimates (Weeks) a m b A - 6 7 8 B - 6 12 18 C - 3 5 7 D B, C 6 9 18 E A, B 5 8 17 F E, D 10 15 20 G E, F 5 6 13 Draw the network diagram and show all calculations for ES-EF-LS-LF and Slack. You will have to find the expected time and variance for each activity. Identify the critical path by highlighting and find out the estimated project completion time, E(T) and the standard deviation for the project completion time, s Determine the probability that the project will be completed in 50 weeks or less. What is the probability that the project will take more than 40 week
Activity | Activity Predecesor Predecessor | A | M | B | Expceted Time | Variance | Slack | Critical Activity | |
A | #NA | 6 | 7 | 8 | 7 | 0.111111 | |||
B | #NA | 6 | 12 | 18 | 12 | 4 | |||
C | #NA | 3 | 5 | 7 | 5 | 0.444444 | |||
D | B,C | 6 | 9 | 18 | 10 | 4 | |||
E | A,B | 5 | 8 | 17 | 9 | 4 | |||
F | E,D | 10 | 15 | 20 | 15 | 2.777778 | |||
G | E,F | 5 | 6 | 13 | 7 | 1.777778 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started