Project Management question please help 4) For the project in the excel file and the MS Project files attached to below, answer the following questions:
Project Management question please help
4) For the project in the excel file and the MS Project files attached to below, answer the following questions: You can use MS Project and then export your answers.
- What are the Work Packages on the critical path?
- Calculate the ES and LS budgets for this project. Schedule all activities to start at their ES time and then at their LS times to answer this question.
- Calculate the actual budget based on the planned schedule.
- As of 4/26, what is the status of the project? Is it on time, on budget, etc. Use the percent complete column to answer this. Show all calculations.
- What is the forecasted completion time and cost of this project if efficiencies do not change.
- What must our efficiencies be to finish on schedule and on budget.
Excel File
MS Project File
item Hm Task Name Duration Planned Start Planned Finish 1 start o days Thu 3/26/20 Thu 3/26/20 2 Summary #1 22 days Thu 3/26/20 Wed 4/29/20 3 Task 1 7 days Thu 3/26/20 Fri 4/3/20 4 task a 5 days Thu 3/26/20 Wed 4/1/20 5 taskc 8 days Mon 4/6/20 Wed 4/15/20 6 task d 4 days Fri 4/10/20 Wed 4/15/20 7 task b 7 days Thu 4/16/20 Fri 4/24/20 8 Task 2 3 days Mon 4/27/20 Wed 4/29/20 9 Summary #2 25 days Fri 4/10/20 Mon 5/11/20 10 Task 3 3 days Fri 4/10/20 Tue 4/14/20 11 taks m 5 days Tue 4/21/20 Mon 4/27/20 12 task n 6 days Tue 4/21/20 Tue 4/28/20 13 taska 2 days Thu 4/30/20 Fri 5/1/20 14 Task 4 4 days Mon 5/4/20 Thu 5/7/20 15 Task 5 2 days Fri 5/8/20 Mon 5/11/20 16 Summary #3 10 days Mon 4/27/20 Mon 5/11/20 17 Task 6 3 days Mon 4/27/20 Wed 4/29/20 18 Task 7 2 days Mon 4/27/20 Tue 4/28/20 19 Task 8 6 days Thu 4/30/20 Thu 5/7/20 20 finish o days Mon 5/11/20 Mon 5/11/20 Predecessors planned cost actual cost percent complete $0.00 $0.00 1 $2,500.00 $2,350.00 100 1 $3,400.00 $3,500.00 100 3,4 $2,100.00 $2,200.00 100 3 $1,100.00 $1,105.00 100 5,6 $9,555.00 $10,100.00 80 5,6 $1,100.00 $500.00 $0.00 3 $2,300.00 $2,200.00 100 10 $1,700.00 $1,500.00 10 $11,445.00 $9,000.00 50 8,12,11 $2,900.00 $0.00 0 13 $6,700.00 $0.00 14 $5,900.00 $0.00 0 O O o 7 O O 7 0 $9,450.00 $10,250.00 $7,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 0 17,18 19,15 0 Task Mode Duration Start Finish Predecessors Baseline Cost 1 1 3,4 3 5,6 5,6 Task Name start Summary #1 Task 1 task a task c task d task b Task 2 - Summary #2 Task 3 taks m task n task a Task 4 Task 5 - Summary #3 Task 6 Task 7 3 o days 25 days 7 days 5 days 8 days 4 days 7 days 3 days 22 days 3 days 5 days 6 days 2 days 4 days 2 days 11 days 3 days 2 days 6 days O days Thu 3/26/20 Thu 3/26/20 Thu 3/26/20 Wed 4/29/20 Thu 3/26/20 Fri 4/3/20 Thu 3/26/20 Wed 4/1/20 Mon 4/6/20 Wed 4/15/20 Fri 4/10/20 Wed 4/15/20 Thu 4/16/20 Fri 4/24/20 Mon 4/27/20 Wed 4/29/20 Fri 4/10/20 Mon 5/11/20 Fri 4/10/20 Tue 4/14/20 Tue 4/21/20 Mon 4/27/20 Tue 4/21/20 Tue 4/28/20 Thu 4/30/20 Fri 5/1/20 Mon 5/4/20 Thu 5/7/20 Fri 5/8/20 Mon 5/11/20 Mon 4/27/24 Mon 5/11/20 Mon 4/27/20 Wed 4/29/20 Mon 4/27/20 Tue 4/28/20 Thu 4/30/20 Thu 5/7/20 Mon 5/11/20 Mon 5/11/20 $0.00 $0.00 $2,500.00 $3,400.00 $2,100.00 $1,100.00 $9,555.00 $1,100.00 $0.00 $2,300.00 $1,700.00 $11,445.00 $2,900.00 $6,700.00 $5,900.00 $0.00 $9,450.00 $10,250.00 $7,500.00 $0.00 10 10 8,12,11 13 14 7 7 Task 8 17,18 19,15 finish item Hm Task Name Duration Planned Start Planned Finish 1 start o days Thu 3/26/20 Thu 3/26/20 2 Summary #1 22 days Thu 3/26/20 Wed 4/29/20 3 Task 1 7 days Thu 3/26/20 Fri 4/3/20 4 task a 5 days Thu 3/26/20 Wed 4/1/20 5 taskc 8 days Mon 4/6/20 Wed 4/15/20 6 task d 4 days Fri 4/10/20 Wed 4/15/20 7 task b 7 days Thu 4/16/20 Fri 4/24/20 8 Task 2 3 days Mon 4/27/20 Wed 4/29/20 9 Summary #2 25 days Fri 4/10/20 Mon 5/11/20 10 Task 3 3 days Fri 4/10/20 Tue 4/14/20 11 taks m 5 days Tue 4/21/20 Mon 4/27/20 12 task n 6 days Tue 4/21/20 Tue 4/28/20 13 taska 2 days Thu 4/30/20 Fri 5/1/20 14 Task 4 4 days Mon 5/4/20 Thu 5/7/20 15 Task 5 2 days Fri 5/8/20 Mon 5/11/20 16 Summary #3 10 days Mon 4/27/20 Mon 5/11/20 17 Task 6 3 days Mon 4/27/20 Wed 4/29/20 18 Task 7 2 days Mon 4/27/20 Tue 4/28/20 19 Task 8 6 days Thu 4/30/20 Thu 5/7/20 20 finish o days Mon 5/11/20 Mon 5/11/20 Predecessors planned cost actual cost percent complete $0.00 $0.00 1 $2,500.00 $2,350.00 100 1 $3,400.00 $3,500.00 100 3,4 $2,100.00 $2,200.00 100 3 $1,100.00 $1,105.00 100 5,6 $9,555.00 $10,100.00 80 5,6 $1,100.00 $500.00 $0.00 3 $2,300.00 $2,200.00 100 10 $1,700.00 $1,500.00 10 $11,445.00 $9,000.00 50 8,12,11 $2,900.00 $0.00 0 13 $6,700.00 $0.00 14 $5,900.00 $0.00 0 O O o 7 O O 7 0 $9,450.00 $10,250.00 $7,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 0 17,18 19,15 0 Task Mode Duration Start Finish Predecessors Baseline Cost 1 1 3,4 3 5,6 5,6 Task Name start Summary #1 Task 1 task a task c task d task b Task 2 - Summary #2 Task 3 taks m task n task a Task 4 Task 5 - Summary #3 Task 6 Task 7 3 o days 25 days 7 days 5 days 8 days 4 days 7 days 3 days 22 days 3 days 5 days 6 days 2 days 4 days 2 days 11 days 3 days 2 days 6 days O days Thu 3/26/20 Thu 3/26/20 Thu 3/26/20 Wed 4/29/20 Thu 3/26/20 Fri 4/3/20 Thu 3/26/20 Wed 4/1/20 Mon 4/6/20 Wed 4/15/20 Fri 4/10/20 Wed 4/15/20 Thu 4/16/20 Fri 4/24/20 Mon 4/27/20 Wed 4/29/20 Fri 4/10/20 Mon 5/11/20 Fri 4/10/20 Tue 4/14/20 Tue 4/21/20 Mon 4/27/20 Tue 4/21/20 Tue 4/28/20 Thu 4/30/20 Fri 5/1/20 Mon 5/4/20 Thu 5/7/20 Fri 5/8/20 Mon 5/11/20 Mon 4/27/24 Mon 5/11/20 Mon 4/27/20 Wed 4/29/20 Mon 4/27/20 Tue 4/28/20 Thu 4/30/20 Thu 5/7/20 Mon 5/11/20 Mon 5/11/20 $0.00 $0.00 $2,500.00 $3,400.00 $2,100.00 $1,100.00 $9,555.00 $1,100.00 $0.00 $2,300.00 $1,700.00 $11,445.00 $2,900.00 $6,700.00 $5,900.00 $0.00 $9,450.00 $10,250.00 $7,500.00 $0.00 10 10 8,12,11 13 14 7 7 Task 8 17,18 19,15 finishStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started