Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Project Management question please help 4) For the project in the excel file and the MS Project files attached to below, answer the following questions:

Project Management question please help

4) For the project in the excel file and the MS Project files attached to below, answer the following questions: You can use MS Project and then export your answers.

  1. What are the Work Packages on the critical path?
  2. Calculate the ES and LS budgets for this project. Schedule all activities to start at their ES time and then at their LS times to answer this question.
  3. Calculate the actual budget based on the planned schedule.
  4. As of 4/26, what is the status of the project? Is it on time, on budget, etc. Use the percent complete column to answer this. Show all calculations.
  5. What is the forecasted completion time and cost of this project if efficiencies do not change.
  6. What must our efficiencies be to finish on schedule and on budget.

Excel File

image text in transcribed

MS Project File

image text in transcribed

item Hm Task Name Duration Planned Start Planned Finish 1 start o days Thu 3/26/20 Thu 3/26/20 2 Summary #1 22 days Thu 3/26/20 Wed 4/29/20 3 Task 1 7 days Thu 3/26/20 Fri 4/3/20 4 task a 5 days Thu 3/26/20 Wed 4/1/20 5 taskc 8 days Mon 4/6/20 Wed 4/15/20 6 task d 4 days Fri 4/10/20 Wed 4/15/20 7 task b 7 days Thu 4/16/20 Fri 4/24/20 8 Task 2 3 days Mon 4/27/20 Wed 4/29/20 9 Summary #2 25 days Fri 4/10/20 Mon 5/11/20 10 Task 3 3 days Fri 4/10/20 Tue 4/14/20 11 taks m 5 days Tue 4/21/20 Mon 4/27/20 12 task n 6 days Tue 4/21/20 Tue 4/28/20 13 taska 2 days Thu 4/30/20 Fri 5/1/20 14 Task 4 4 days Mon 5/4/20 Thu 5/7/20 15 Task 5 2 days Fri 5/8/20 Mon 5/11/20 16 Summary #3 10 days Mon 4/27/20 Mon 5/11/20 17 Task 6 3 days Mon 4/27/20 Wed 4/29/20 18 Task 7 2 days Mon 4/27/20 Tue 4/28/20 19 Task 8 6 days Thu 4/30/20 Thu 5/7/20 20 finish o days Mon 5/11/20 Mon 5/11/20 Predecessors planned cost actual cost percent complete $0.00 $0.00 1 $2,500.00 $2,350.00 100 1 $3,400.00 $3,500.00 100 3,4 $2,100.00 $2,200.00 100 3 $1,100.00 $1,105.00 100 5,6 $9,555.00 $10,100.00 80 5,6 $1,100.00 $500.00 $0.00 3 $2,300.00 $2,200.00 100 10 $1,700.00 $1,500.00 10 $11,445.00 $9,000.00 50 8,12,11 $2,900.00 $0.00 0 13 $6,700.00 $0.00 14 $5,900.00 $0.00 0 O O o 7 O O 7 0 $9,450.00 $10,250.00 $7,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 0 17,18 19,15 0 Task Mode Duration Start Finish Predecessors Baseline Cost 1 1 3,4 3 5,6 5,6 Task Name start Summary #1 Task 1 task a task c task d task b Task 2 - Summary #2 Task 3 taks m task n task a Task 4 Task 5 - Summary #3 Task 6 Task 7 3 o days 25 days 7 days 5 days 8 days 4 days 7 days 3 days 22 days 3 days 5 days 6 days 2 days 4 days 2 days 11 days 3 days 2 days 6 days O days Thu 3/26/20 Thu 3/26/20 Thu 3/26/20 Wed 4/29/20 Thu 3/26/20 Fri 4/3/20 Thu 3/26/20 Wed 4/1/20 Mon 4/6/20 Wed 4/15/20 Fri 4/10/20 Wed 4/15/20 Thu 4/16/20 Fri 4/24/20 Mon 4/27/20 Wed 4/29/20 Fri 4/10/20 Mon 5/11/20 Fri 4/10/20 Tue 4/14/20 Tue 4/21/20 Mon 4/27/20 Tue 4/21/20 Tue 4/28/20 Thu 4/30/20 Fri 5/1/20 Mon 5/4/20 Thu 5/7/20 Fri 5/8/20 Mon 5/11/20 Mon 4/27/24 Mon 5/11/20 Mon 4/27/20 Wed 4/29/20 Mon 4/27/20 Tue 4/28/20 Thu 4/30/20 Thu 5/7/20 Mon 5/11/20 Mon 5/11/20 $0.00 $0.00 $2,500.00 $3,400.00 $2,100.00 $1,100.00 $9,555.00 $1,100.00 $0.00 $2,300.00 $1,700.00 $11,445.00 $2,900.00 $6,700.00 $5,900.00 $0.00 $9,450.00 $10,250.00 $7,500.00 $0.00 10 10 8,12,11 13 14 7 7 Task 8 17,18 19,15 finish item Hm Task Name Duration Planned Start Planned Finish 1 start o days Thu 3/26/20 Thu 3/26/20 2 Summary #1 22 days Thu 3/26/20 Wed 4/29/20 3 Task 1 7 days Thu 3/26/20 Fri 4/3/20 4 task a 5 days Thu 3/26/20 Wed 4/1/20 5 taskc 8 days Mon 4/6/20 Wed 4/15/20 6 task d 4 days Fri 4/10/20 Wed 4/15/20 7 task b 7 days Thu 4/16/20 Fri 4/24/20 8 Task 2 3 days Mon 4/27/20 Wed 4/29/20 9 Summary #2 25 days Fri 4/10/20 Mon 5/11/20 10 Task 3 3 days Fri 4/10/20 Tue 4/14/20 11 taks m 5 days Tue 4/21/20 Mon 4/27/20 12 task n 6 days Tue 4/21/20 Tue 4/28/20 13 taska 2 days Thu 4/30/20 Fri 5/1/20 14 Task 4 4 days Mon 5/4/20 Thu 5/7/20 15 Task 5 2 days Fri 5/8/20 Mon 5/11/20 16 Summary #3 10 days Mon 4/27/20 Mon 5/11/20 17 Task 6 3 days Mon 4/27/20 Wed 4/29/20 18 Task 7 2 days Mon 4/27/20 Tue 4/28/20 19 Task 8 6 days Thu 4/30/20 Thu 5/7/20 20 finish o days Mon 5/11/20 Mon 5/11/20 Predecessors planned cost actual cost percent complete $0.00 $0.00 1 $2,500.00 $2,350.00 100 1 $3,400.00 $3,500.00 100 3,4 $2,100.00 $2,200.00 100 3 $1,100.00 $1,105.00 100 5,6 $9,555.00 $10,100.00 80 5,6 $1,100.00 $500.00 $0.00 3 $2,300.00 $2,200.00 100 10 $1,700.00 $1,500.00 10 $11,445.00 $9,000.00 50 8,12,11 $2,900.00 $0.00 0 13 $6,700.00 $0.00 14 $5,900.00 $0.00 0 O O o 7 O O 7 0 $9,450.00 $10,250.00 $7,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 0 17,18 19,15 0 Task Mode Duration Start Finish Predecessors Baseline Cost 1 1 3,4 3 5,6 5,6 Task Name start Summary #1 Task 1 task a task c task d task b Task 2 - Summary #2 Task 3 taks m task n task a Task 4 Task 5 - Summary #3 Task 6 Task 7 3 o days 25 days 7 days 5 days 8 days 4 days 7 days 3 days 22 days 3 days 5 days 6 days 2 days 4 days 2 days 11 days 3 days 2 days 6 days O days Thu 3/26/20 Thu 3/26/20 Thu 3/26/20 Wed 4/29/20 Thu 3/26/20 Fri 4/3/20 Thu 3/26/20 Wed 4/1/20 Mon 4/6/20 Wed 4/15/20 Fri 4/10/20 Wed 4/15/20 Thu 4/16/20 Fri 4/24/20 Mon 4/27/20 Wed 4/29/20 Fri 4/10/20 Mon 5/11/20 Fri 4/10/20 Tue 4/14/20 Tue 4/21/20 Mon 4/27/20 Tue 4/21/20 Tue 4/28/20 Thu 4/30/20 Fri 5/1/20 Mon 5/4/20 Thu 5/7/20 Fri 5/8/20 Mon 5/11/20 Mon 4/27/24 Mon 5/11/20 Mon 4/27/20 Wed 4/29/20 Mon 4/27/20 Tue 4/28/20 Thu 4/30/20 Thu 5/7/20 Mon 5/11/20 Mon 5/11/20 $0.00 $0.00 $2,500.00 $3,400.00 $2,100.00 $1,100.00 $9,555.00 $1,100.00 $0.00 $2,300.00 $1,700.00 $11,445.00 $2,900.00 $6,700.00 $5,900.00 $0.00 $9,450.00 $10,250.00 $7,500.00 $0.00 10 10 8,12,11 13 14 7 7 Task 8 17,18 19,15 finish

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting What the Numbers Mean

Authors: David H. Marshall, Wayne W. McManus, Daniel F. Viele

10th edition

9780077515904, 007802529X, 77515900, 978-0078025297

More Books

Students also viewed these Accounting questions

Question

4. Identify the challenges facing todays organizations

Answered: 1 week ago