Project managers are expected to ensure that appropriate trade - offs are made between the time, cost, and requirements of the project. Multiple Choice performance
Project managers are expected to ensure that appropriate tradeoffs are made between the time, cost, and requirements of the project.
Multiple Choice
performance
quality
specifications
functional
scope