Question

1 Approved Answer

Project managers recognise that time, cost and resource estimates must be accurate to ensure effective project planning, scheduling and controlling (Larson & Gray, 2014).

 

Project managers recognise that time, cost and resource estimates must be accurate to ensure effective project planning, scheduling and controlling (Larson & Gray, 2014). (b) (c) Discuss FIVE (5) guidelines, with rationale, for developing useful work package estimates for project planning purposes. (10 marks) Explain why accurate estimates are critical to effective project management. Demonstrate the uses of estimates to further support your explanation. (10 marks) Describe and contrast the FIVE (5) top-down approach of estimating. (10 marks)

Step by Step Solution

3.41 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

a Five guidelines for developing useful work package estimates for project planning purposes 1 Break Down the Work Package Divide the work package into smaller manageable tasks or activities Breaking ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions