project managment 13 :Draw the PERT Diagram, identify the critical path, and calculate slack time for the following * (o ) ( ) * (5
project managment 13 :Draw the PERT Diagram, identify the critical path, and calculate slack time for the following * (o ) ( ) * (5 ) Activity Preceding Activity Time (weeks) 2 A B 3 11 4 5 E B 2 F B 3 G 4 UO H 6 E 3 1 4 HI F G K 8