Project Phoenix costs $1.25 million and yields annual cost savings of $200,000 for seven years. The assets involved in the project can be salvaged for
Project Phoenix costs $1.25 million and yields annual cost savings of $200,000 for seven years. The assets involved in the project can be salvaged for $100,000 at the end of the project. Ignoring taxes, what is the payback period for Project Phoenix?
Step by Step Solution
There are 3 Steps involved in it
Step: 1