Question
Project Planning Data (Hrs.) Your project consists of activities A to F , and it is planned as follows : Duration Labour Activity Dependency (
Project Planning Data (Hrs.) Your project consists of activities A to F , and it is planned as follows : Duration Labour Activity Dependency ( Wks . ) A Starts now 1 180 B Follows A 1 180 Follows A 1 180 D Follows C 1 160 E Starts 2 wks after D is completed 1 160 F Follows E 1 160 In addition The cost of labour is $ 87 / hour . A phase end review meeting is planned right after activity D is completed at a cost of $ 6.500 Actual Project Performance and the end of 3.5 Weeks Completed : Activities and phase review meeting Activities C and E 115 hrs and 125 hrs respectively of actual work is done Activity D : 45 % completed The total amount spent up to this point is $ 61,500 in total Calculate at the end of Weeks 1 Budget at completion : 5 MARKS 2 Planned value 5 MARKS 3 Eamed value 5 MARKS 4 CPI ( four decimal points ) AND INTERPRET THE RESULT 2 MARKS ( four decimal points ) AND INTERPRET THE RESULT MARKS 6 What do you currently expect the total project cost to be at the end of the project ( 2 MARKS 7 From the end of 3.5 weeks , how much MORE do you expect to cost to finish the project ? 2 MARKS What should be the future cost performance level required to finish the project on budget 2 MARKS You can also insert SHOW YOUR CALCULATIONS No calculations , no marks You can use the HTML Editor to enter your answer in tables Images and files
Prolect Plannlng Pata Your prolect consists of activities A to F. and it is dlanned as follows: In addition: - The cost of labour is $87 hour. - A phase end review meeting is planned right after activity D is completed at a cost of $6.500. Actual Prolect Performance and the end of 3.5 Weeks: - Compieled: Activities A, B, and phase review meeting - Activities C and E: 115 hrs. and 125 hrs. respectively of actual work is done. - Activity D: 45% completed - The total amount spent up to this point is $61,500 in total Calculate at the end of 3.5 Weeks: 1. Budget at completon: 5 MARKS 2. Planned value: 5 MARKS 3. Eamed value 5 MARKS. 4 CPI (four decimal points) AND INTERPRET THE RESULT 2 MARKS 5. SPI (four decimal points) AND INTERPRET THE RESULT. 2 MARKS 6 What do you curcently expect the tolal propet cost to be at the end of the project? ( 2 MARKS) 7 From the end of 35 weoks, how much MORE to you expect to cost to finish the project? 12 MARKS) 8. What should be the future cost performance icuel required to finish the project on budget. 2 MARKS) SHOW YOUR CALCULATIONS. No calculations, no marks You can use the HTML. Editor to enter your answer in fables. You can also insert images and filesStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started