Project Resource Leveling Assignment 1. Draw the Activity on Node (AON) network diagram, representing the project activities and their dependencies. 2. Make a bar chart
Project Resource Leveling Assignment
1. Draw the Activity on Node (AON) network diagram, representing the project activities and their dependencies.
2. Make a bar chart and resource diagram illustrating resource allocation to the scheduled activities (refer to class example 2 for drawing a resource diagram and creating a legend).
3. Adjust (level) the resources so that the maximum number of laborers used per day does not exceed seven.
Resource Leveling: Example 2 * A subcontractor needs to install flooring to two areas: * Area one: has old vinyl tile that has to be taken out and replaced by new vinyl tile, and * Area two: concrete slab that needs to be topped with ceramic tile. * The subcontractor has six laborers and we assume for simplicity- that any laborer can do any activity * The project is broken into the activities as shown Resource Leveling: Example 2 Activity Description Purchase & Deliver materials Remove old vinvl tile (R Install ceramic tile (R Install new vinvl tile (R1) Clean up & inspect C,D ' Resource Leveling: Example2 | Activity Description Purchase & Deliver materials m Remove old vinyl tile (R1) | | | C Install ceramic tile (R2) l m Install new vinyl tile (R1) Clean up & inspect Example2 mono Solution 8 9 10 11 12 13 14 Davs Laborers Resource Legend: Max Regular use of resource available per day Overuse of resource 8 9 10 11 12 13 14 Davs Laborers Resource Max available per day Legend: Non-critical activity Critical activity mon looks Float X Used float 3 5 6 8 9 10 11 12 13 14 Days Laborers Resource Max available per davStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started