Question
Project risk is a measure of the ________________ and the __________________ of not achieving a defined project goal. Select one: uncertainty and cost damage and
Project risk is a measure of the ________________ and the __________________ of not achieving a defined project goal.
Select one:
uncertainty and cost
damage and time
cost and time
Impact and cost
probability and consequence
Question 2 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Future events or outcomes that are favorable are called:
Select one:
Risks
Opportunities
Surprises
Contingencies
None of the above
Question 3 Not yet answered Points out of 5.00 Not flaggedFlag question Question text In Project Management, future outcomes or consequences that have a probability of occurrence and are unfavorable are called:
Select one:
Risks
Opportunities
Surprises
Contingencies
None of the above
Question 4 Not yet answered Points out of 5.00 Not flaggedFlag question Question text The cause, or source of danger, of a risk event is known as a/an:
Select one:
Opportunity
Probability
Insurance policy
Hazard
All of the above
Question 5 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Risk management is:
Select one:
the act or practice of dealing with risk
proactive rather than reactive
not a separate project office activity assigned to a risk management department
1 and 3
All of the above
Question 6 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Based on the table constructed below, which strategy has the highest expected value?
PAYOFF TABLE (PROFIT IN MILLIONS)
Strategy
Scenario 1 (25 percent)
Scenario 2 (50 percent)
Scenario 3 (25 percent)
S1
80
50
120
S2
80
80
80
S3
160
120
-20
S4
20
40
20
S5
-20
0
-60
Select one:
S1
S2
S3
S4
S5
Question 7 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Based on the data in the table in Question 6 above, which strategy has the highest expected value with no chance for a loss?
Select one:
S1
S2
S3
S4
S5
Question 8 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Using the "maximax" or Hurwicz criterion (e.g., go for broke or risk-lover), which strategy in Question 6 should be selected?
Select one:
S1
S2
S3
S4
S5
Question 9 Not yet answered Points out of 5.00 Not flaggedFlag question Question text The process of examining the program areas and each critical technical process to identify and document the associated risk is known as:
Select one:
Risk identification
Risk response
Lessons learned or risk control
Risk quantification
None of the above
Question 10 Not yet answered Points out of 5.00 Not flaggedFlag question Question text If the minimum payoffs of four different strategies A1, A2, A3, and A4 are -10, -5, 0, and -20 respectively, which strategy would a project manager choose using the "maximum" or Wald criterion (risk avoider)?
Select one:
Not enough information to answer this question
Strategy A1
Strategy A2
Strategy A3
Strategy A4
Question 11 Not yet answered Points out of 5.00 Not flaggedFlag question Question text A medium level of risk associated with a risk event always translates into a ________________ percent probability that this risk event will occur.
Select one:
60
30
40
50
You cannot determine the exact probability from the information provided
Question 12 Not yet answered Points out of 5.00 Not flaggedFlag question Question text When changing the scope of a project to lower the associated risk, a project manager should consider the impact on:
Select one:
The schedule
The cost
The quality
All of the above
1 and 2 only
Question 13 Not yet answered Points out of 5.00 Not flaggedFlag question Question text A project manager states, "I will actively take the necessary measures required to actively mitigate this risk. I will do what is expected." He is exercising the ____________ method of risk reduction
Select one:
Tranfer (deflection)
Avoidance
Control (e.g., mitigation)
Assumption (retention)
Wald
Question 14 Not yet answered Points out of 5.00 Not flaggedFlag question Question text A Risk Mapping Matrix (such as a Probability/Impact Matrix) is an example of:
Select one:
Quantitative Risk Analysis
Risk Transference
Risk MItigation
Qualitative Risk Analysis
None of the above.
Question 15 Not yet answered Points out of 5.00 Not flaggedFlag question Question text When the project's risk event probabilities are multiplied by their respective consequences (in dollars) and then are added together, the sum represents the:
Select one:
Project manager's risk aversion quotient
Earned Value
The expected value of the project
2 and 3
1 and 2
Question 16 Not yet answered Points out of 5.00 Not flaggedFlag question Question text What is the expected value of a project based on the following data:
Outlook
Value
Probability
Marginal
$60,000
0.25
Good
$100,000
0.50
Poor
$40,000
0.25
Select one:
$190,000
$75,000
$100,000
$120,000
None of the above
Question 17 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Per Kerzner, "No risk management plan" is a typical risk event for which life cycle phase?
Select one:
Project approval
Preliminary and detailed planning
Execution
Closure
None of the above.
Question 18 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Given the following possible loss outcomes of a project event, find the expected loss:
Loss Probability $0 0.2 $1,000 0.3 $2,000 0.5
Select one:
$0
$1,300
$2,000
$3,000
None of the above
Question 19 Not yet answered Points out of 5.00 Not flaggedFlag question Question text Given the following possible profit and loss outcomes of a project, find the expected profit or (loss):
Profit or (Loss) Probability ($1,000) 0.1 $0 0.1 $1,000 0.3 $2,000 0.5
Select one:
($1,000)
$1,000
$2,000
$1,200
None of the above
Question 20 Not yet answered Points out of 5.00 Not flaggedFlag question Question text The Expected Value of a project's risk can be defined as:
Select one:
The sum of the probabilities of project risk events times the sum of consequences of those risks
The sum of the products of the probabilities of each project risk event times its consequence
The sum of the consequences of all project risk events
The sum of the probabilities of all project risk events
None of the above
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started