Project Scheduling A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to
Project Scheduling
A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the task.
Task | Duration | Depend on |
T1 | 1 | |
T2 | 3 | |
T3 | 5 | |
T4 | 3 | T1 |
T5 | 2 | T1 |
T6 | 2 | T1,T3 |
T7 | 1 | T2,T3 |
T8 | 3 | T4,T5,T6 |
T9 | 3 | T5,T7 |
T10 | 2 | T7 |
T11 | 2 | T8 |
T12 | 3 | T8,T9 |
T13 | 2 | T10 |
Answer the questions below. These activities are intended to develop and assess your understanding of the method, so please do not use a software project management tool such as Microsoft Project to assist in either drawing the diagrams or in computing solutions.
Questions :
Assume 4 engineers, Bob, Sue mary and frank, work on the project and each task is worked by one engineers only. Allocate tasks to them to complete the project in the shortest possible time. Show this graphically on a staff allocation chart.
The sum of task duration is 32 weeks which when divided by 4 engineers gives a value of 8 weeks, which one might expert to be minimum time to complete the project. explain why it is not possible to complete project in 8 weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started