Project Status: Side (1): Done @ $2,500 Side (2): Done @ $2,500 Side (3): Done @ $3,000 Side (4): 50% @ $1,500 Roof: Not yet
Project Status:
Side (1): Done @ $2,500
Side (2): Done @ $2,500
Side (3): Done @ $3,000
Side (4): 50% @ $1,500
Roof: Not yet started
What is the Estimated at Completion (EAC) for this project?
A. | EAC = $15,000 | |
B. | EAC = $17,143 | |
C. | EAC = $18,000 | |
D. | EAC = $16,304 |