Question
Project Time Management: Case Study Tony Prince is the project manager for the Recreation and Wellness Intranet Project. Team members include you, a programmer/analyst and
Project Time Management: Case Study
Tony Prince is the project manager for the Recreation and Wellness Intranet Project. Team members include you, a programmer/analyst and aspiring project manager; Patrick, a network specialist; Nancy, a business analyst; and Bonnie, another programmer/analyst. Other people are supporting the project from other departments, including Yusaff from human resources and Cassandra from finance. Assume that these are the only people who can be assigned and charged to work on project activities. Recall that your schedule and cost goals are to complete the project in six months for under $200,000.
Project Time Management: Assignment (2 Tasks)
Review the WBS and Gantt chart you created previously. Propose three to five additional activities that would help you estimate resources and durations. Now, identify at least eight milestones for the Recreation and Wellness Intranet Project. Remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone. Add your activities and milestones to your Gantt chart, creating a new Gantt chart. Estimate the task durations and enter dependencies as appropriate. Remember that your schedule goal for the project is six months. Copy the Gantt chart and network diagram to a word document.
After your Gantt chart and network diagram, summarize how you would assign people to each activity. Include a table or matrix listing how many hours each person would work on each task. These resource assignments should make sense given the duration estimates you made. Remember that duration estimates are not the same as effort estimates because they include elapsed time.
Project Cost Management: Case Study
Tony Prince and his team are working on the Recreation and Wellness Intranet Project. They have been asked to refine the existing cost estimate for the project so they can evaluate supplier bids and have a solid cost baseline for evaluating project performance. Recall that your schedule and cost goals are to complete the project in six months for under $200,000.
Project Cost Management: Assignment (3 Tasks)
Prepare a one-page cost model for the project described in the Running Case, similar to the model below:
Types of Cost Estimates | |||
Type of Estimate | When Done | Why Done | How Accurate |
Rought order of magnitude (ROM) | Very early in the projec tlife cycle, often 35 years before project completion | Provides estimate of cost for selection decisions | 50% to +100% |
Budgetary | Early, 12 years out | Puts dollars in the budget plans | 10% to +25% |
Definitive | Later in the project, less than 1 year out | Provides details for purchases, estimates actual costs | 5% to +10% |
Source: TABLE 7-2 Types of cost estimates Cengage Learning 2014
Use the following WBS, and be sure to document your assumptions in preparing the cost model. Assume a labor rate of $100/hour for the project manager and $60/hour for other project team members. Assume that none of the work is outsourced, labor costs for users are not included, and there are no additional hardware costs. The total estimate should be $200,000.
a. Project management
b. Requirements definition
c. Web site design
o Registration for recreational programs
o Registration for classes and programs
o Tracking system
o Incentive system
d. Web site development
o Registration for recreational programs
o Registration for classes and programs
o Tracking system
o Incentive system
e. Testing
f. Training, rollout, and support
Using this cost model you created, prepare a cost baseline by allocating the costs by WBS for each month of the project.
Assume that you have completed three months of the project. The BAC was $200,000 for this six-month project. You can also make the following assumptions:
PV = $120,000 EV = $100,000 AC = $90,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started