Project TOC is to be performed in 4 quarterly phases P 1 = $ 2 0 , 0 0 0 , P 2 = $

Project TOC is to be performed in 4 quarterly phases P1= $20,000, P2= $70,000, P3= $50,000, P4= $50,000. As per the Cost Management Plan a kill point assessment will be done at the half way duration. This assessment is scheduled for the end of 6 months
Project leads report that 55% of the Project Work is completed at this point. Finance reports that $93,400 has been spent.
What is the Variance in Cost that should be reported?
Question 13 options:
$5,400
$11,100
$10,500
$5,300

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Company Audit In A Budget Internal Audit For Financial Managers

Authors: Pramod Kesav N

1st Edition

B09QXF42M2

More Books

Students also viewed these Accounting questions