Question

1 Approved Answer

Project will be delivered in 2 waves - Wave 1 & Wave 2 . It has 4 workstreams ( WS 1 , WS 2 ,

Project will be delivered in 2 waves - Wave 1 & Wave 2. It has 4 workstreams (WS1, WS2, WS3, WS4) with interdependencies. Each workstream has pBT (Design, Build and Test) phase and has respective deliverables Each deliverable goes through below defined stages, and % Calculate the CPI (Cost Performance Index)[2 Marks)2. Calculate the SPI (Schedule Performance Index)2 Marks)3. Calculate the ETC (Estimate to Complete)[1 Mark]completion for each gate is as follows: Defined Stages for each deliverable % Complete In-progress Draft Completed Internal Review Completed Formal Review Completed Sign-off 25%60%80%90%100% Below are the 5 deliverables for the workstream Calculate the CPI (Cost Performance Index)[2 Marks)
2. Calculate the SPI (Schedule Performance Index)2 Marks)
3. Calculate the ETC (Estimate to Complete)[1 Mark]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Redesigning Innovative Healthcare Operation And The Role Of Knowledge Management

Authors: Murako Saito

1st Edition

1605662844, 9781605662848

More Books

Students also viewed these General Management questions