Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Project - X has an approved budget of $ 1 0 , 0 0 0 . Activity - A has a planned Value of $

Project-X has an approved budget of $10,000.
Activity-A has a planned Value of $500
Activity-B has a planned value of $900
Activity-C has a planned value of $800
Activities A and B are both complete, but Activity-C is only 75% complete
The actual costs thus far equal $2,500
What is the Estimate at Completion (EAC), assuming that all remaining work is completed according to original estimates:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Today

Authors: Terri A. Scandura, Kim Gower

1st Edition

ISBN: 1506385877, 978-1506385877

More Books

Students also viewed these General Management questions