Project Z has a current budget of $ 2 0 million. The project is working on a 2 0 - month schedule. After month 6
Project Z has a current budget of $ million. The project is working on a month schedule. After month the following performance data is available: Actual Cost AC $ million; Planned Value PV $ million; Earned Value $ million. What would be the Estimate at Completion, assuming that current cost performance will continue for the rest of the project?
A $ million
B $ million
C $ million
D $ million