Question

1 Approved Answer

Project Z has a current budget of $ 2 0 million. The project is working on a 2 0 - month schedule. After month 6

Project Z has a current budget of $20 million. The project is working on a 20-month schedule. After month 6, the following performance data is available: Actual Cost (AC)= $6.5 million; Planned Value (PV)= $6.8 million; Earned Value = $7.1 million. What would be the Estimate at Completion, assuming that current cost performance will continue for the rest of the project?
A. $20.0 million
B. $19.4 million
C. $21.8 million
D. $18.3 million

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finance for Executives Managing for Value Creation

Authors: Gabriel Hawawini, Claude Viallet

4th edition

9781133169949, 538751347, 978-0538751346

More Books

Students also viewed these Finance questions