Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Provide a detailed analysis of the status of this project. Describe any required courses of action. BUDGETED vs ACTUAL COST: REASONS FOR DIFFERENCES: The differences

Provide a detailed analysis of the status of this project. Describe any required courses of action.

BUDGETED vs ACTUAL COST:

REASONS FOR DIFFERENCES: The differences in cost/schedule are:

CV & CEV:

CPI:

FORECASTS: ?If efficiency (CPI) remains the same ?Even if all remaining work is completed as budgeted (CPI=1) ?To complete the project at the budgeted cost

COURSE(S) OF ACTION:

TIME-COST TRADEOFF EXERCISE

Based on the figure shown above, answer the following questions:

a. What is the total cost and duration of the project if all activities are performed in their normal time?

b. What is the per-week crash cost for:

(1) Activity A?

(2) Activity B?

(3) Activity C?

(4) Activity D?

c. What is the shortest possible project completion time?

d. What is the lowest possible cost to achieve the time given in answer c? (Provide the new total cost and the cost and durations used for each activity to achieve this cost and schedule.) ?New total cost: ?Activity A: New cost: New duration: ?Activity B: New cost: New duration: ?Activity C: New cost: New duration: ?Activity D: New cost: New duration:

image text in transcribedimage text in transcribed
Search 1:52PM Sun Apr 7 59% 479_assign4.docx . . . CIS 479 - Assignment 4 [15pts] Individual Assignment * *Submit answers in a Word document via Blackboard by due date (see Bb). Project Analysis: o Complete the attached Project Analysis Exercise . Time-Cost Tradeoff: o Complete the attached Time-Cost Tradeoff Exercise PROJECT ANALYSIS EXERCISE Based on the following tables, answer questions a through h. Week TBC 1 2 3 4 5 Task 1 30 20 10 Task 2 40 20 10 10 Task 3 50 30 20 Task 4 25 10 15 BUDGETED COSTS *Numbers are in $thousands Week 1 2 3 4 5 ACTUAL Task 1 25 10 COSTS Task 2 15 20 Task 3 42 Task 4 *Numbers are in Sthousands Week 1 2 3 4 5 PERCENTAGE Task 1 60 100 OF WORK Task 2 50 100 COMPLETE Task 3 90 Task 41M1:22 49 [ ] &~ 479_assign4.pdf h. Provide a detailed analysis of the status of this project. Describe any required courses of action. BUDGETED CTUAL COST: REASONS FOR DIFFERENCES: The differences in cost/schedule are: vV EV: CPL: FORECASTS: If efficiency (CPI) remains the same * Even if all remaining work is completed as budgeted (CPI=1) To complete the project at the budgeted cost ACTION: TIME- T TRADEOFF EXERCISE A B N =6, $40,000 N =7, $55,000 C =4, 844,000 C =5, 865,000 Start Finish e C D N=6,$30,000 | N=8, $65,000 C =6, $30,000 C =6, $69,000 * Times shown in weeks Based on the figure shown above, answer the following questions: a. What is the total cost and duration of the project if all activities are performed in their normal time? b. What is the per-week crash cost for: (1) Activity A? (2) Activity B? (3) Activity C? (4) Activity D? c. What is the shortest possible project completion time? d. What is the lowest possible cost to achieve the time given in answer ? (Provide the new total cost and the cost and durations used for each activity to achieve this cost and schedule.) * New total cost: * Activity A: New cost: New duration: * Activity B: New cost: New duration: * Activity C: New cost: New duration: N et UL O1L

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Financial Management

Authors: Eugene F. Brigham, Joel F. Houston

Concise 3rd Edition

003033263X, 9780030332630

More Books

Students also viewed these General Management questions

Question

Understand some techniques for evaluating the HRM function

Answered: 1 week ago