PS . 7 4 Bell computer is planning to launch a new high - end server. Nine steps or tasks are required to assemble this
PS Bell computer is planning to launch a new highend server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be units and there are three hour shifts available each day to meet this production quota.
Task Req'd Time in minutes Predecessor
A None
B A
C B
D B
E A
F C D
G F
H E
I G H
What is the total time in minutes to produce one server?