Answered step by step
Verified Expert Solution
Question
1 Approved Answer
PS.73 Golden Oldies is a small company that burns music CDs for non-technical senior citizens. The table below contains information on the steps required to
PS.73 Golden Oldies is a small company that burns music CDs for non-technical senior citizens. The table below contains information on the steps required to burn and package a CD. (Their equipment is quite old, hence, the long burn time.) No specific demand numbers are available, however, the cycle time should not exceed 29 minutes in order to meet demand requirements. What is the total time (in minutes) to produce one CD? What is the takt time (in minutes) for this production line? (Round your answer to a whole number.) Which task should you assign to workstation 1 ? A and B B and C C and D C and E What is the theoretical minimum number of workstations for this production line? Given your task assignments to workstations, what is the actual number of workstations required? What is the cycle time (in minutes) for this production line? What is the combined idle time (in minutes) for this production line? What is the overall efficiency for this production line? (Write your answer as a percentage, and display your answer to two decimal places.) %
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started