Q 1 to Q 7 are based on this problem. The Bill of Material and the following Tables are given. Part of the solutions in

Q1 to Q7 are based on this problem.
The Bill of Material and the following Tables are given. Part of the solutions in the table is provided so that you can verify your calculation as you go. The empty cell does not necessarily mean the value is zero. It means the value of the cell is not given. The value could be zero or any other number.
W13 BOM chart
Part Number
Current On-Hand
Schedule Receipts (SRs)
Lot-Sizing Rule
Lead Time
Due
Quantity
A
50
0
FOQ, Q=50
1 week
B
40
0
FOP, 2 weeks
2 weeks
300
50
2
50
Lot-for-lot
1 weeks
500
40
0
Lot-for-lot
4 weeks
Part A
1
2
3
4
5
6
7
8
Gross requirement
10
15
20
20
10
15
20
15
Scheduled receipts
Projected on-hand
50
40
25
5
A
-
-
-
-
Net requirement
10
15
15
Planned order receipts
B
C
Planned order release
Which of the following statement is not true?
Group of answer choices
The Low Level Code (LLC) of part A and part B are both 0.
The LLC of part 100 is 1.
The LLC of part 300 and part 600 are both 2.
The LLC of part 400 is 3.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Competitiveness and Globalization, Concepts and Cases

Authors: Michael A.Hitt, R.Duane Ireland, Robert E.Hoskisson

11th edition

978-1285425177, 1285425170, 978-1305200333, 978-1285425184

More Books

Students also viewed these General Management questions

Question

What is the return on stockholders' equity (after tax) ratio?

Answered: 1 week ago