Q 2 . The activity involved in a certain project have been identified as follows: job time ( weeks ) no of men required preceding

Q2. The activity involved in a certain project have been identified as follows:
job time(weeks) no of men required preceding requirements
A 51
B 101 A
C 82 A
D 63 B,C
E 71 B,C
F 42 E
G 42 D,F
H 21 G
a. For the above project draw the network (using the MS word line function) and determine the critical path.
b. If there are three men available at any one time how long would the project take and how would you allocate the men to the activities?
c. If there are no restrictions on the amount of labour available, explain how you would schedule the activities?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Linear Algebra and Its Applications

Authors: David C. Lay

4th edition

321791541, 978-0321388834, 978-0321791542

More Books

Students also viewed these General Management questions