Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Q 2 . The activity involved in a certain project have been identified as follows: job time ( weeks ) no of men required preceding
Q The activity involved in a certain project have been identified as follows:
job timeweeks no of men required preceding requirements
A
B A
C A
D BC
E BC
F E
G DF
H G
a For the above project draw the network using the MS word line function and determine the critical path.
b If there are three men available at any one time how long would the project take and how would you allocate the men to the activities?
c If there are no restrictions on the amount of labour available, explain how you would schedule the activities?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started