Question

1 Approved Answer

Q . 3 Draw AON diagram to represent the following project. Calculate occurrence times of events ( i . e . activity times ) .

Q.3 Draw AON diagram to represent the following project. Calculate occurrence times of events (i.e. activity times). Determine the critical path and the degree of criticality of other float paths.
\table[[\table[[Activit],[y]],Description,\table[[Immediate],[Predecessors]],\table[[Time],[(weeks)]]],[A,Build internal components,-,2],[B,Modify roof and floor,-,3],[C,Construct collection stack,A,2],[D,Pour concrete and install frame,A, B,4],[E,Build high-temperature burner,C,4],[F,Install pollution control system,C,3],[G,Install air pollution device,D, E,5],[H,Inspect and test,F, G,2]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability And Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson, Paul Griffin

4th Canadian Edition

0137319169, 978-0137319169

More Books

Students also viewed these General Management questions

Question

If you completed the Excel track, what is the Significance F value?

Answered: 1 week ago

Question

Describe in plain English what the results of this t-test mean.

Answered: 1 week ago