Question

1 Approved Answer

Q 3 ) Mohammad is the project manager of a project to build 2 labour houses each month and completed after 1 2 months. Each

Q3) Mohammad is the project manager of a project to build 2 labour houses each month and completed after 12 months. Each house plan to cost SAR10000.20 labour houses have been built after 9 months and CPI is 0.85106 a) What is the actual cost of the project right now?b) What is the projects estimate at completion?c) How much more money will it take to complete the project?d) How is the project performing?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology Conservation And Management

Authors: Anthony R. E. Sinclair, John M. Fryxell, Graeme Caughley

2nd Edition

1405107375, 978-1405107372

More Books

Students also viewed these General Management questions

Question

Show that the last sentence of the preceding paragraph is correct.

Answered: 1 week ago

Question

Examine the diffuculty of adding a prposed swap rs , rt

Answered: 1 week ago

Question

How do you talk about your complaining customers?

Answered: 1 week ago