Q 3 Using the table that follow, schedule the project based on two resource constraints. All relationships between the activities are finish - to -

Q3
Using the table that follow, schedule the project based on two resource constraints. All relationships between the activities are finish-to-start and the lags are zero. You are asked to update the schedule based on the resource constraint (a bar chart schedule).
\table[[Activity,Predecessor,Duration,Resource Rate/Day],[Resource I,Resource II],[A,Start,4,3,10],[B,A,I,8,5],[C,A,3,6,4],[D,B,5,7,8],[E,C,I,1,3],[F,D,E,4,9,2],[Finish,G,,,],[,Availabl,,10,12]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Information Technology

Authors: Carol Brown, Daniel DeHayes, Jeffrey Hoffer, Wainright Marti

7th Edition

132146320, 978-0132146326

More Books

Students also viewed these General Management questions