Q . 6 . WetLimeStone has two cement production plants ( P 1 and P 2 ) located 5 0 0 k m s of

Q.6. WetLimeStone has two cement production plants (P1 and P2) located 500kms of each other. Cement from the two production plants are shipped by rail wagons to two regional distribution centres (D1 and D2), and then to three supply houses (S1, S2 and S3) by trucks and vans.
The production capacities of plants P1 and P2 are 8000 and 7000 tons/week respectively, and the demand at supply houses S1, S2 and S3 are 4500,3500 and 3000 tons/week respectively. The unit cost of transporting cement (Rs/ton) between the production plants and distribution centres, and between the distribution centres and supply houses is given in the table below.
\table[[From/To,D1,D2,S1,S2,S3],[P1,4,7,,,],[P2,5,7,,,],[D1,,,6,4,5],[D2,,,2,3,6]]
Due to limited availability of transport and prior commitments, no more than 1500 tons week can be shipped from D2 to S1, and a minimum of 400 tons week must be shipped from D1 to S2.
Write a set of linear programming equations to minimize total cost of transportation, and draw a neat network diagram.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Databases questions