Question
Q1). Develop a cost-benefit analysis for Fast Parts Delivery Stores information system upgrade project by examining the list of cost factors and summary of values
Q1). Develop a cost-benefit analysis for Fast Parts Delivery Stores information system upgrade project by examining the list of cost factors and summary of values for the new information system below, then completing part a.
SCENARIO: The benefits of the new system are expected to come from a few sources: data consistency, increased integration with suppliers, and improved security. These benefits are estimated to be $62,000 in the first year of the systems operation and will grow at a rate of 10% each year thereafter. An additional benefit from the system is based on lower inventory levels (due to improved integration). Savings from lower inventory levels are expected to be $30,000 per year for each year of the projects life. Using a format similar to the cost-benefit analysis spreadsheet (given in the resources) that summarizes this projects cash flow and assuming a five-year useful life after the project is developed, develop a cost-benefit analysis of the project. Compute the present value of the cash flows using an interest rate of 9%. What is the NPV for this project? What is the ROI for this project? What is the break-even point? Based on the economic analysis, should this project be approved to proceed further?
a). Complete the Cost-Benefit Analysis Template below using information from the provided scenario.
COST BENEFIT ANALYSIS (ROI and NPV) TEMPLATE FOR SOFTWARE PROJECTS |
ITEM | 2007 ($) | 2008 ($) | 2009 ($) | 2010 ($) | 2011 ($) | Total ($) | |
BENEFITS | |||||||
Increased Sales | |||||||
Reduction in customer calls | |||||||
Reduced Inventory Costs | |||||||
Total Benefits | |||||||
Present Value (PV) of Benefits | |||||||
Cumulative PV of All Benefits | |||||||
DEVELOPMENT COSTS | |||||||
2 servers @ $125,000 | |||||||
Printers/Networking Gear | |||||||
Software Licenses | |||||||
Server Software | |||||||
Development Labor | |||||||
Total Development Costs | |||||||
OPERATIONAL COSTS | |||||||
Hardware | |||||||
Software | |||||||
Operational Labor | |||||||
TOTAL OPERATIONAL COSTS | |||||||
TOTAL COSTS | |||||||
Present Value (PV) of Costs | |||||||
Cumulative PV of All Costs | |||||||
TOTAL BENEFITS - TOTAL COSTS | |||||||
Yearly NPV | |||||||
Cumulative NPV | |||||||
ROI | |||||||
NPV (Net Present value) | |||||||
Break-even Point | |||||||
Intangible Benefits |
COST FACTORS AND SUMMARY OF VALUES :
Development Costs: Personnel
2 Systems Analysts 400 hours/ea @ $50/hour
4 Programmer Analysts 250 hours/ea @ $35/hour
1 GUI Designer 200 hours/ea @ $40/hour
1 Telecommunications Specialist 50 hours/ea @ $50/hour
1 System Architect 100 hours/ea @ $50/hour
1 Database Specialist 15 hours/ea @ $45/hour
1 System Librarian 250 hours/ea @ $15/hour
Development Costs: Training
4 team members need Oracle training registration @ $3,500/person
Development Costs: New Hardware and Software
1 Development server $18,700
1 Server software (OS, misc.) $1,500
1 DBMS server software $7,500
7 DBMS client software $950/client
Annual Operating Costs: Personnel
2 Programmer Analysts 125 hours/ea @ $35/hour
1 System Librarian 20 hours/ea @ $15/hour
Annual Operating Costs: Hardware, Software, and Miscellany
1 Maintenance agreement for server $995
1 Maintenance agreement for server $525
Pre-printed forms 15,000/year @ $0.22/form
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started