Question

1 Approved Answer

Q1). Develop a cost-benefit analysis for Fast Parts Delivery Stores information system upgrade project by examining the list of cost factors and summary of values

Q1). Develop a cost-benefit analysis for Fast Parts Delivery Stores information system upgrade project by examining the list of cost factors and summary of values for the new information system below, then completing part a.

SCENARIO: The benefits of the new system are expected to come from a few sources: data consistency, increased integration with suppliers, and improved security. These benefits are estimated to be $62,000 in the first year of the systems operation and will grow at a rate of 10% each year thereafter. An additional benefit from the system is based on lower inventory levels (due to improved integration). Savings from lower inventory levels are expected to be $30,000 per year for each year of the projects life. Using a format similar to the cost-benefit analysis spreadsheet (given in the resources) that summarizes this projects cash flow and assuming a five-year useful life after the project is developed, develop a cost-benefit analysis of the project. Compute the present value of the cash flows using an interest rate of 9%. What is the NPV for this project? What is the ROI for this project? What is the break-even point? Based on the economic analysis, should this project be approved to proceed further?

a). Complete the Cost-Benefit Analysis Template below using information from the provided scenario.

COST BENEFIT ANALYSIS (ROI and NPV) TEMPLATE FOR SOFTWARE PROJECTS
ITEM 2007 ($) 2008 ($) 2009 ($) 2010 ($) 2011 ($) Total ($)
BENEFITS
Increased Sales
Reduction in customer calls
Reduced Inventory Costs
Total Benefits
Present Value (PV) of Benefits
Cumulative PV of All Benefits
DEVELOPMENT COSTS
2 servers @ $125,000
Printers/Networking Gear
Software Licenses
Server Software
Development Labor
Total Development Costs
OPERATIONAL COSTS
Hardware
Software
Operational Labor
TOTAL OPERATIONAL COSTS
TOTAL COSTS
Present Value (PV) of Costs
Cumulative PV of All Costs
TOTAL BENEFITS - TOTAL COSTS
Yearly NPV
Cumulative NPV
ROI
NPV (Net Present value)
Break-even Point
Intangible Benefits

COST FACTORS AND SUMMARY OF VALUES :

Development Costs: Personnel

2 Systems Analysts 400 hours/ea @ $50/hour

4 Programmer Analysts 250 hours/ea @ $35/hour

1 GUI Designer 200 hours/ea @ $40/hour

1 Telecommunications Specialist 50 hours/ea @ $50/hour

1 System Architect 100 hours/ea @ $50/hour

1 Database Specialist 15 hours/ea @ $45/hour

1 System Librarian 250 hours/ea @ $15/hour

Development Costs: Training

4 team members need Oracle training registration @ $3,500/person

Development Costs: New Hardware and Software

1 Development server $18,700

1 Server software (OS, misc.) $1,500

1 DBMS server software $7,500

7 DBMS client software $950/client

Annual Operating Costs: Personnel

2 Programmer Analysts 125 hours/ea @ $35/hour

1 System Librarian 20 hours/ea @ $15/hour

Annual Operating Costs: Hardware, Software, and Miscellany

1 Maintenance agreement for server $995

1 Maintenance agreement for server $525

Pre-printed forms 15,000/year @ $0.22/form

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Complete Guide To Property Finance

Authors: Richard W J Brown

1st Edition

1739832027, 978-1739832025

More Books

Students also viewed these Finance questions