Q-1 The manager of a National Forest is about to undertake a reforestation project in a burned out area. The project will involve the following

Q-1 The manager of a National Forest is about to undertake a reforestation project in a burned out area. The project will involve the following six activities: ACTIVITY IMMEDIATE PREDECESSOR(S) DURATION ESTIMATES (days) OPTIMISTIC MOST LIKELY PESSIMISTIC Start - U Start 35 50 65 V Start 28 40 52 W U, V 26 35 44 X V 28 40 52 Y X 26 29 38 Z Y, W 36 60 84 End Z What is the probability that the critical path for this project will be completed within 200 days? a. 0.9544. b. 0.8413 c. 0.9974 d. 0.9987 e. 0.9772

Q-2 A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the following activities:

Activity Immediate Predecessor(s) Durations (weeks)
to tm tp
Start -
A Start 11 20 29
B A 2 5 8
C A 18 30 42
D B 7 10 13
E Start 31 40 43
End C, D, E

What is the probability that the critical path for this project will be completed within 52 weeks?

a.

0.3108

b.

0.1554

c.

0.8277

d.

0.6554

e.

0.3466

Q-3 A project manager for Durable Construction Co. is about to build a house involving the following activities:

Activity Immediate Predecessor(s) Durations (days)
Optimistic Most likely Pessimistic
Start -
A Start 44 50 56
B Start 45 60 75
C A 42 45 48
D A, B 31 40 49
E C 27 36 39
F E, D 58 70 82
End F

What is the probability that the critical path for this project will be completed within 210 days?

a.

0.9544

b.

0.5000

c.

0.9987

d.

0.8413

e.

0.9772

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions