Question

1 Approved Answer

Q1) X Produces bicycle tire pumps on a production line. The time to perform the 6 tasks in producing the pump take 42.8 minutes. Ten

Q1) X Produces bicycle tire pumps on a production line. The time to perform the 6 tasks in producing the pump take 42.8 minutes. Ten pumps per hour must be produced and 45 minutes per hour are productive. The cycle time will be -

a) 4 minutes

b) 4.5 minutes

c) 45 minutes

d) 428 minutes

Referring to question no. 1, The minimum number of work stations required will be -

a) 9

b) 9.51

c) 12

d) 13

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ignite Your Lyfe Self Esteem Through Entrepreneurship

Authors: Jameelah Wilkerson

1st Edition

979-8458529761

More Books

Students also viewed these General Management questions