Q1. You have been hired by lnnovative Solutions to plan the development of a web site for Sydney Flowers (SF). They have decided to set

Q1. You have been hired by lnnovative Solutions to plan the development of a web site for Sydney Flowers (SF). They have decided to set it up on a local server and some of the test team need operational training. You have identified the major task headings, durations and dependencies as shown in the table below. Everyone will be working 5-day weeks.

a. Draw a network diagram showing all the tasks and their dependencies (abbreviate their names if necessary). Arrange the tasks to achieve the shortest time to complete the project and determine the number of weeks it will take to complete the project.

b. Calculate the slack or float time for each activity, on the understanding that many tasks can be run in parallel if dependencies permit

c. Finally, list the task numbers that form the critical path.

Task Duration Depend on
A. Proposal sign-off 0 days
B. Detailed Requirement Analysis 3 3 days A
C. hardware and software analysis 1 day B
D. Develop Website 10 days B
E. acquire and setup hardware and software 5 days C
F. Server administer trained 3 days B
G. Web system loaded onto server 3 days D, E
H. Test website 1 days G
I. Evaluate training requirement 4 days F, H
J. develop training document 3 days I
K. database created on server 5 days E, H
L. test database 1 day K
M. Train KF employees 4 days J, L
N. data Migration 5 days L, M

O. user acceptance testing

2 days

F, N

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Tools For Business Decision Making

Authors: Paul D. Kimmel

4th Canadian Edition

0470155353, 978-0470155356

More Books

Students also viewed these Accounting questions

Question

What is meant by planning or define planning?

Answered: 1 week ago

Question

Define span of management or define span of control ?

Answered: 1 week ago

Question

What is meant by formal organisation ?

Answered: 1 week ago

Question

What is meant by staff authority ?

Answered: 1 week ago