Q2: (20 Points) Using the data given below, calculate the measured depths, vertical depths and horizontal displacements at: 1. EOB 2. End of tangent
Q2: (20 Points) Using the data given below, calculate the measured depths, vertical depths and horizontal displacements at: 1. EOB 2. End of tangent section 3. EOD 4. Target 5. Azimuth West coordinate = 8900 ft = Kick-off depth 1,000 ft = Build-up rate 3.0 degrees/100 ft North coordinate - 6415 ft Final inclination angle in reservoir = 21 TVD at target = 15635 ft Declination -4 west Drop-off rate 7.0 degrees/100 ft