Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Q2. E-Scoot plans to manufacture electric scooters for urban commuters. The company expects to have two models, the Commuter and the Range models. The company

Q2. E-Scoot plans to manufacture electric scooters for urban commuters. The company expects to have two models, the Commuter and the Range models. The company will use activity-based costing to apply its estimated $145,000 of overhead costs to its products. Information about its overhead follows:

Activity (Cost Driver)

Estimated MOH

Expected Activity

Total

Commuter

Range

Assembly (Labour Hours)

$20,000

10,000

6,000

4,000

Quality control (Inspection Hours)

35,000

2,000

600

1,400

Parts Admin (Number of Parts)

90,000

100

40

60

$145,000

The following cost data is known:

Commuter

Range

Direct Materials

$600

$900

Direct Labour

250

400

Number of units produced

250 units

150 units

The company has not yet determined its planned selling price, but knows that the average price for competitors of the Commuter model is $1,200. For the Range model, competitors are priced at $1,700 on average.

Required:

a.) Compute the activity rates for each activity.

b.) Determine the expected unit cost of each product.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Courageous Auditing Beyond Compliance Towards Being A Catalyst For Change

Authors: Kathy Rees

1st Edition

0648958108, 978-0648958109

More Books

Students also viewed these Accounting questions

Question

Draw a sketch of the graph of the given inequality. 3x + 2y + 6 > 0

Answered: 1 week ago