# Q2 .Pendarvis Company uses a job-order costing system and has the following information for the first week of June: 1.Direct labor and direct materials
#Q2 .Pendarvis Company uses a job-order costing system and has the following information for the first week of June:
1.Direct labor and direct materials used:
Job No. Direct Material Direct Labor Hours
498 $1,500 116
506 960 16
507 415 18
508 345 42
509 652 24
511 308 10
512 835 30
---------------------------------------------------------------------------------
Total $5,015 256
2.The direct labor wage rate is $4 per hour.
3.The overhead rate is $5 per direct labor hour.
4.Actual overhead costs for the week, $1,480.
5.Jobs completed: Nos. 498, 506, and 509.
6.The factory had no work in process at the beginning of the week.
Required:
A.PrepareA a summary that will show the total cost assigned to each job.
B.Compute the amount of overhead over- or underapplied during the week.
C.Calculate the cost of the work in process at the end of the week.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started