Q3) Calculate standard deviation of project length Activity Optimistic time T 0 Most likely Tm Pessimistic time Tp 1-2 1 1 7 1-3 1 4

Q3) Calculate standard deviation of project length

Activity

Optimistic time

T0

Most likely

Tm

Pessimistic time

Tp

1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Management

Authors: Andrew J DuBrin

10th Edition

0996757872, 9780996757874

More Books

Students also viewed these General Management questions

Question

What are the key aspects of Popeyess franchise model?

Answered: 1 week ago

Question

What reward will you give yourself when you achieve this?

Answered: 1 week ago