Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Q3. Project Crashing Use the information provided in Table 4 to answer the project crashing questions. Table 4 Activity # ID D, Days (NT, CT)
Q3. Project Crashing Use the information provided in Table 4 to answer the project crashing questions. Table 4
Activity # | ID | D, Days (NT, CT) | Cost (NC, CC) | Slope | Maximum Crash Time |
A1 | - | 3,2 | 150,200 | ||
A2 | A1 | 3,2 | 100,200 | ||
A3 | A1 | 4,2 | 200,320 | ||
A4 | A2 | 3,1 | 200,320 | ||
A5 | A3 | 4,3 | 200,270 | ||
A6 | A4, A5 | 1,1 | 150,150 |
1. Identify cost slope and maximum crash time - update Table 4.
2. Identify Critical Path. 3. What is the project finish time using NT?
4. Crash the above project to complete in 8 days. a.Provide the network diagram and critical path after completing the project crashing.
b.What is the direct cost to complete the above project in 8 days?