Question

1 Approved Answer

Q3. Project Crashing Use the information provided in Table 4 to answer the project crashing questions. Table 4 Activity # ID D, Days (NT, CT)

Q3. Project Crashing Use the information provided in Table 4 to answer the project crashing questions. Table 4

Activity # ID D, Days (NT, CT) Cost (NC, CC) Slope Maximum Crash Time
A1 - 3,2 150,200
A2 A1 3,2 100,200
A3 A1 4,2 200,320
A4 A2 3,1 200,320
A5 A3 4,3 200,270
A6 A4, A5 1,1 150,150

1. Identify cost slope and maximum crash time - update Table 4.

2. Identify Critical Path. 3. What is the project finish time using NT?

4. Crash the above project to complete in 8 days. a.Provide the network diagram and critical path after completing the project crashing.

b.What is the direct cost to complete the above project in 8 days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mathematical Applications for the Management Life and Social Sciences

Authors: Ronald J. Harshbarger, James J. Reynolds

11th edition

9781337032247, 9781305465183, 1305108043, 1337032247, 1305465180, 978-1305108042

More Books

Students also viewed these Mathematics questions