Q4.4 (Algo) 12 tasks to 4 workers [4.1, 4.2, 4.3, 4.4] Consider the following tasks that must be assigned to four workers on a conveyor-paced

Q4.4 (Algo) 12 tasks to 4 workers [4.1, 4.2, 4.3, 4.4]

Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There is unlimited demand.

Time to Complete Task (seconds)
Task 1 30
Task 2 25
Task 3 15
Task 4 20
Task 5 15
Task 6 20
Task 7 50
Task 8 15
Task 9 20
Task 10 25
Task 11 15
Task 12 20

The current conveyor-paced assembly-line configuration assigns the workers in the following way:

Worker 1: Tasks 1, 2, 3

Worker 2: Tasks 4, 5, 6

Worker 3: Tasks 7, 8, 9

Worker 4: Tasks 10, 11, 12

a. What is the capacity of the current line? (Round your final answer to two decimal places.)

b. What is the direct labor content? (Round your final answer to one decimal place.)

c. What is the average labor utilization (do not consider any transient effects such as the line being emptied before breaks or shift changes)? (Round your final answer to two decimal places.)

d. How long would it take to produce 130 units, starting with an empty system? (Round your final answer to two decimal places.)

e. Assume the firm has hired a fifth worker. The task assignments for the five workers are shown below. What is the capacity of this line now? (Round your final answer to two decimal places.)

Worker Task(s)
1 1,2
2 3,4,5
3 6,7
4 8,9
5 10,11,12

f. Again, assume the firm has hired a fifth worker. The task assignments for the five workers are shown below. What is the capacity of this line now? (Round your final answer to two decimal places.)

Worker Task(s)
1 1,2
2 3,4,6
3 5,8,10
4 7
5 9,11,12

g. Now assume the firm is using eight workers. The task assignments for the eight workers are shown below. What is the capacity of this line now? (Round your final answer to two decimal places.)

Worker Task(s)
1 1
2 2,3
3 4,5
4 6
5 7
6 8,9
7 10,11
8 12

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Truth About The Drug Companies How They Deceive Us And What To Do About It

Authors: Marcia Angell

1st Edition

0375760946, 978-0375760945

More Books

Students also viewed these General Management questions