Q5. / The project schedule has the following characteristics: 4 points Activity Time (weeks) Activity A B C D E F G H I Path
Q5. / The project schedule has the following characteristics: 4 points Activity Time (weeks) Activity A B C D E F G H I Path 1-2 1-4 1-3 2-4 2-6 4-5 3-5 3-6 5-6 Duration 8 10 8 10 16 17 18 14 9 a) Construct the network, and Find the critical path (CP). b) Compute E and L for each event. c) Find the total float time for each activity. 1 Add file