Q6. You are 4 months (end of month 4) into a 7-month commercial renovation project for one of Suncor's (The Bow) floor renovations. The original

image text in transcribed

image text in transcribed

Q6. You are 4 months (end of month 4) into a 7-month commercial renovation project for one of Suncor's (The Bow") floor renovations. The original budget is $150,000 and you have completed 40% of the work. At this time, you should have completed 57% of the work. Actual costs to date are $90,000 and you just found out that there is a mold issue with the drywall and needs to be fixed (it's a health regulation issue which has to be addressed regardless of budget constrains, otherwise work cannot continue). The cost will be $9,000. This cost of mold remediation is above and beyond and could not had been predicted beforehand. This will add 2 weeks to your schedule. (10 points) One of the reasons that you are overbudget is the fact that you have had to pay higher labor costs due to a mini labor shortage happening in Alberta. This is expected to continue for the forceable future. Calculate BAC, BCWP, ACWP, EAC, ETC and CPI (to 3 decimal points) as of end of month 4. How many months will it take to complete the project (##.## format)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Total Quality Safety Management And Auditing

Authors: Michael B. Weinstein

1st Edition

1566702836, 978-1566702836

More Books

Students also viewed these Accounting questions

Question

=+14.4. 1 Let C be the set of continuity points of F.

Answered: 1 week ago