Question
Assume the following information for an IT project. Probability of Failure Consequences of Failure Maturity = .7 Cost = .9 Complexity = .7 Schedule =
Assume the following information for an IT project.
Probability of Failure Consequences of Failure
Maturity = .7 Cost = .9
Complexity = .7 Schedule = .7
Dependency = .5 Performance = .3
Client Concerns = .5 Future Business = .5
Programmer Skill = .3
Calculate the overall risk factor for this project. Would you assess this level of risk as low, moderate, or high? Why?
Step by Step Solution
3.52 Rating (162 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project Management Achieving Competitive Advantage
Authors: Jeffrey K. Pinto
4th edition
133798070, 978-0133798074
Students also viewed these Business Communication questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App