Question 1 ( 2 0 marks ) Sunshine Construction Company Limited engaged in a construction project. The project was begun in 2 0 2 2
Question marks
Sunshine Construction Company Limited engaged in a construction project. The project was
begun in and completed in with contract price of $ Cost and other data
relating to the project was presented below:
Assume that the Company uses the PERCENTAGEOFCOMPLETION METHOD for
revenue recognition. The Company's financial yearend is December.
Required: Answers should be rounded to two decimal places if necessary
a Calculate the gross profits losses recognized for the financial years and
respectively. Show your workings clearly
marks
b Prepare the journal entries necessary to record the above information on the Company's
books during
marks
c Prepare an extracted Statement of Financial Position for showing items related to
this longterm construction project.
marks
d Compute the gross profits losses recognized for the financial years and
assuming the company uses the COST RECOVERY METHOD to account for the
longterm contract.
marks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started