Question 1 ( 2 0 marks ) Sunshine Construction Company Limited engaged in a construction project. The project was begun in 2 0 2 2

Question 1(20 marks)
Sunshine Construction Company Limited engaged in a construction project. The project was
begun in 2022 and completed in 2025 with contract price of $2,000,000. Cost and other data
relating to the project was presented below:
Assume that the Company uses the PERCENTAGE-OF-COMPLETION METHOD for
revenue recognition. The Company's financial year-end is 31 December.
Required: (Answers should be rounded to two decimal places if necessary)
(a) Calculate the gross profits (losses) recognized for the financial years 2022,2023,2024 and
2025, respectively. (Show your workings clearly)
(4 marks)
(b) Prepare the journal entries necessary to record the above information on the Company's
books during 2024.
(9 marks)
(c) Prepare an extracted Statement of Financial Position for 2024 showing items related to
this long-term construction project.
(3 marks)
(d) Compute the gross profits (losses) recognized for the financial years 2022,2023,2024 and
2025, assuming the company uses the COST RECOVERY METHOD to account for the
long-term contract.
(4 marks)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Construction Accounting And Financial Management

Authors: Steven J. Peterson

1st Edition

0131109391, 978-0131109391

More Books

Students also viewed these Accounting questions

Question

3.3

Answered: 1 week ago