QUESTION 1 (30) 1.1 INFORMATION: Britelite Manufacturers produces a product which has the following standard costs: Material A: 3 kilograms at R20 per kilogram Material
QUESTION 1 (30)
1.1 INFORMATION:
Britelite Manufacturers produces a product which has the following standard costs:
Material A: 3 kilograms at R20 per kilogram
Material B: 5 kilograms at R15 per kilogram
Direct labour: 8 hours at R10 per hour
Fixed overheads: R120 000
Budgeted production: 9 000 units
Actual results for February 2019 were as follows:
Material A: 32 500 kg at R22 per kilogram
Material B: 54 000 kg at R14 per kilogram
Direct labour: 88 000 hours at R12 per hour
Fixed overheads: R132 000
Production: 10 000 units
REQUIRED:
Calculate the following:
1.1.1 Material mix variance (6)
1.1.2 Material yield variance (6)
1.1.3 Fixed manufacturing overheads volume capacity variance (3)
1.1.4 Fixed manufacturing overheads volume efficiency variance (2)
1.2 REQUIRED:
Use the information provided below to calculate the following:
1.2.1 Idle time variance (3)
1.2.2 Labour mix variance (7)
1.2.3 Labour yield variance (3)
Indicate whether each variance is favourable or unfavourable.
INFORMATION:
Standard labour costs for Electro Manufacturers to manufacture 2 000 units:
400 hours at R70 per hour
200 hours at R35 per hour
Actual labour costs incurred to produce 1 900 units:
290 hours at R R65 per hour
170 hours at R32 per hour
Idle time represents 10% of the recorded labour hours
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started