Question ( 1 ) [ 6 Marks ] Your Plant is operating in batch mode, Calculate the batch cycle time and number of batch per
Question Marks
Your Plant is operating in batch mode, Calculate the batch cycle time and number of batch per day through drawing the Gantt Chart: a Sequential production schedule, b Overlapping batches.
Table Batch Data
tableStepDuration hDryingReactionEvaporationDistillation
Step by Step Solution
There are 3 Steps involved in it
Step: 1