Question 1 7 . ( 2 5 points ) Project Control - Earned Value ( EV ) The following bar chart shows the activities to

image text in transcribed
Question 17.(25 points)
Project Control - Earned Value (EV)
The following bar chart shows the activities to complete a 6-month project. After 3 months on
the job (July 1), the contractor has completed 20% of Activity F,80% of Activity C, and 40% of
Activity E. Activities A, B, and D are fully completed. These activities have accumulated a cost
of $535.
For this point in time, calculate the following:
a) The budgeted cost of work performed (BCWP)=
b) The budgeted cost of work scheduled (BCWS)=
c) Cost variance (as a percentage)=CV(%)=
d) Is the project over or under budget?
e) Schedule variance (as a percentage)=SV(%)=
f) Is the project ahead or behind schedule?
g) Estimated Cost at Completion =EAC=.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Accounting for Governmental and Not for Profit Organizations

Authors: Paul A. Copley

13th edition

125974101X, 978-1259741012

More Books

Students also viewed these Accounting questions