Question
1 Approved Answer
Question 1 7 . ( 2 5 points ) Project Control - Earned Value ( EV ) The following bar chart shows the activities to
Question points
Project Control Earned Value EV
The following bar chart shows the activities to complete a month project. After months on
the job July the contractor has completed of Activity F of Activity C and of
Activity E Activities A B and D are fully completed. These activities have accumulated a cost
of $
For this point in time, calculate the following:
a The budgeted cost of work performed
b The budgeted cost of work scheduled
c Cost variance as a percentage
d Is the project over or under budget?
e Schedule variance as a percentage
f Is the project ahead or behind schedule?
g Estimated Cost at Completion EAC
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started